Project Timeline
PRE-DESIGN |
|
1.1 STUDY - November 2010 |
|
1.2 SCHEMATIC APPROACH - November 2010 |
|
1.3 INTEGRATED DESIGN SESSION - November 2010 |
|
1.4 PRELIMINARY PROPOSAL - February 2011 |
|
1.5 INTEGRATED DESIGN SESSION - February 2011 |
|
1.6 INTEGRATED DESIGN SESSION - February 2011 |
DESIGN - PHASE 1 |
|
2.1 BUILDING PERMIT - "DTAC"- March - June 2011 |
|
2.2 BUILDING PERMITS - May - June 2011 |
|
2.3 INTEGRATED DESIGN SESSION - April 2011 |
|
2.4 INTEGRATED DESIGN SESSION - May 2011 |
|
2.5 TECHNICAL PROJECT - PT - 1 - June 2011 |
|
2.6 INTEGRATED DESIGN SESSION - June 2011 |
|
2.7 TECHNICAL PROJECT - PT - 2 - July 2011 |
|
2.8 INTEGRATED DESIGN SESSION - June 2011 |
|
2.9 INTEGRATED DESIGN SESSION - January 2012 |
CONSTRUCTION - late June 2011 - August 2012 - in progress |
COMMISSIONING AND REOPENING - May 2012 |
OPERATION AND MAINTENANCE - starting May 2012 |
INTERIOR DESIGN AND LANDSCAPING - PHASE 2 |
|
6.1 INTERIOR DESIGN - concept - in progress |
|
6.2 INTERIOR DESIGN WORKSHOP - September 2012 |
|
6.3 LANDSCAPING - concept |
|
6.4 LANDSCAPING - planting - September 2012 |